Metsec SFS infill wall with RCM Y-Wall sheathing board, and Knauf Fire Panel (2x12.5mm) lining.
SFS infill wall with plasterboard lining.
Metsec SFS infill wall with RCM Y-Wall sheathing board, and Knauf Fire Panel (2x12.5mm) lining.
Resistance to Fire
voestalpine Metsec’s fire test data for infill walling is to BS EN 1364‑1: 2015. All test data is based on unique UKAS accredited tests and UKAS accredited scope of testing.
Fire Performance - Non-Boundary Wall: 60,90,120 Minutes (E)
Test Reference - Internal: P100456-1016
Fire Performance - Boundary Wall: 60 Minutes (EI)
Test Reference - Internal: P100456-1016
Test Reference - External: P102396-1007
MetWALL Perform Warranty
MetWALL Perform, an industry changing warranty giving architects, developers and contractors reassurance when specifying through wall products on voestalpine Metsec steel frame systems.
This is an important addition to voestalpine Metsec’s unique Framing range providing warranted, UKAS tested wall combinations, enabling clients to select the most cost-effective performance design solutions.
Metsec Decarb
voestalpine Metsec’s commitment to sustainable construction is emphasised by the introduction of responsibly sourced steel to our product ranges. Manufactured by processes which minimise carbon output by using state-of-the-art electric arc furnaces powered by renewable energy, rather than the traditional blast furnace which burn fossil fuels, Metsec Decarb promises to make a significant contribution towards reducing the carbon dioxide and carbon footprint of the building project.
System Codes
Y1-N90-K22, Y1-N100-K22, Y1-N120-K22, Y1-N150-K22, Y1-N180-K22, Y1-N200-K22, Y1-N210-K22, Y1-N240-K22, Y1-N270-K22, Y1-N300-K22, Y1-N350-K22
Finish | Galvanized Guidance for specification option: Steel. |
Material | Steel Plasterboard |
Shape | Other |
Length | Bespoke |
Width | Bespoke |
Height | Bespoke |
Warranty description | 30 year |
Uniclass | |
CAWS | G10/20 Steel framing system G10/150 Steel framing system |
Product range |
System performance | Structural design supervision and checking. |
Framing members | Cold-formed galvanized steel sections. |
Connections | |
Connection fasteners | Self drilling tek screws. |
Anchors to concrete and masonry | |
Type of anchor | By structural engineer's design. |
Movement joints | Deflection allowance at the top of the wall. |
Insulation | Not required. Between framing. Guidance for specification option: Insert detailed requirements. |
Sheathing board | RCM Y-Wall - 12 mm. |
Framing | Metsec SFS 90 mm stud depth. Guidance for specification option: Typically at 600 mm centres. Manufacturer guidanceSee Insulation if insulation between framing is required. |
Inner layer | Knauf Fire Board, 12.5 mm. |
Face layer | Knauf Fire Board, 12.5 mm. |
Fasteners | Drywall screws. |
System accessories | Flatstrap / partition brace. Guidance for specification option: Required behind horizontal board joints. |
Internal face | 90/ 120 minutes (insulation/ integrity). |
External face | 60/ 120 minutes (insulation/ integrity). |
Fire performance | 60 minutes (boundary wall); 120 minutes (non-boundary wall). |
Thermal performance (U-value maximum) | Variable. |
Air tightness | Variable. |
Dimensional constraints | 127 mm. |
Contains Red List materials | No |
Country of product manufacture | United Kingdom |
Material | Steel Plasterboard |
Recyclability | SFS Light Gauge Steel 95-100% |
Recycled contentAs defined in clause 7.8 of BS EN ISO 14021 | 60 % |
Platform | Compatible | Version |
---|---|---|
- | 1 |
BSI Kitemark
BIM Level 2 Kitemark - For Design and Construction Phase
BSI Kitemark
BSI Kitemark™ for BIM Objects
EPD
Environmental Product Declaration EPD - SFS
ISO 9001 Quality Management
ISO 9001:2015 Quality Management System
BSI Kitemark
UKCA Certificate of Conformity of the Factory Production Control
CCPI System
CCPI Light Gauge Steel Framing Systems
Metsec’s lightweight steel framing system, SFS, is being used in the creation of a new £346m riverside residential development in the Barking and Dagenham area of London
Metsec’s SFS steel framing system has helped to create a seamless finish to the façade of a new state-of-the-art custody centre and strategic policing hub for Devon and Cornwall Constabulary.
Metsec SFS infill wall with British Gypsum Glasroc X sheathing board, British Gypsum Gyproc plasterboard
Metsec SFS infill wall with British Gypsum Glasroc X sheathing board, British Gypsum Gyproc plasterboard, Knauf Rocksilk RainScreen insulation
Metsec SFS Infill Wall with British Gypsum Glasroc X sheathing board, British Gypsum Gyproc plasterboard, Rockwool Duoslab insulation
Metsec SFS infill wall with Euroform Easyboard sheathing board, British Gypsum Gyproc plasterboard
Metsec SFS infill wall with Euroform Versaroc sheathing board, British Gypsum Gyproc plasterboard
Metsec SFS infill wall with Euroform Versaroc sheathing board, British Gypsum Gyproc plasterboard, and Rockwool Duoslab Insulation
Metsec SFS infill wall with Euroform Versaroc sheathing board, Knauf plasterboard, Rockwool Duoslab insulation
Metsec SFS infill wall with Klasse G-Board sheathing board, British Gypsum Gyproc plasterboard
Metsec SFS infill wall with Knauf Windliner sheathing board, and British Gypsum Gyproc plasterboard
Metsec SFS infill wall with Knauf Windliner sheathing board, Knauf plasterboard, and Knauf Rocksilk RainScreen insulation